Civil Works


Sector 17A is designed for Institutional and residential land use with an area of approximately 425.9 Ha. Authority has completed internal and external development (roads of 120m and 30m, sewer, drains, water supply, electrification). A 3000 Kl capacity UGR has also been completed. The sector has fourteen Institutional plots, one recreational, one township and over twenty seven corporate office plots.

It is a residential sector of area approximately 1846 Ha. The whole area is divided into pockets. A total of 12748 number of plots are employed in Sector-18, in which internal and external development works (sewerage, drainage, road and electrification) are in progress. In addition to the above, construction of OHTs having capacity 2700 Kilolitres and 2400 Kilolitres and 4 tube wells work is complete.

24m wide internal road work at Sector 18

In Sector-20 a total of 10981 residential plots are planned in total area of 1485 Ha. The sector is divided in 19 pockets, in which internal and external development works (roads, sewer, drains, water supply, electrification) are under  progress in all the pockets.The construction work of four OHTs and eight tube wells work is complete.

f4ea74a6-1ded-4953-984c-752ad56cdd27
447a37d1-2eea-488c-a6ae-5c53de0eac0a

Sector 22D  is a residential, township, group housing sector of approximately 440.8 Ha area. About 5100 affordable houses, 1320 LIG houses, 768 MIG houses are constructed along with shops and office complex. Internal and external development works (sewerage, drainage, road and electrification) are  in progress. One OHT and three UGRs have been completed.

Sector 22E is an institutional and corporate office (commercial) sector of approximately 345 Ha area. It has a total of 73 institutional plots, 3 facilities plots and 16 corporate office plots. Internal and external development works (roads, sewerage, drainage, water supply and electrification) are in progress. One OHT and three UGRs have been completed.

It is primarily an industrial sector of approximately 697 Ha area and a  total of 42 nos. of plots have been planned under the sector, under which the plots of Dharampal Satpal Ltd., Vivo Mobile India Pvt. Ltd. and Patanjali Ayurveda Ltd. Industries have been allotted. Internal and external development works of the sector (water supply, drainage, sewerage, roads and electrification) are partially completed. The work of 2600 Kilolitre UGR and 2500 Kilolitre OHT has been completed.

OHT at Sector 24
C.W.R at Sector 24

Sector 26 A is designed for one township project and two group housing projects. A 60 Mtr wide road has been constructed by Authority in front of these projects. 

Sector 26 B is an institutional sector. It is situated on 30 Mtr wide road parallel to 100 Mtr wide Yamuna Expressway. In this sector one plot of 100 Acre area is planned. External development work (Road, Drain and sewer) has been already completed.

It is an industrial sector of approximately 670 Ha area. Provision has been made for industrial plots for MSME, Apparel & Handicraft Park under the sector. 45 meter, 30 meter and 24 meter wide roads have been planned. Under the development works, development works of water supply, RCC drain, sewer line road etc. are in progress.

Road work at Sector 32
Road work at Sector 32
Drain work at Sector 33
Drain work at Sector 33

It is an industrial sector of approximately 497.5 Ha area having a total of 1888 plots.Internal and external development works (roads, sewerage, drainage, water supply and electrification) are completed. Two tubewells are completed and a UGR of 2600 Kilolitres capacity is under construction.

(a) 120m wide Road

The construction work of length 13.80 km is complete. On the right side of Yamuna Expressway up to 8.80 km has been constructed, on which various Group Housing, Industrial Unit, VIVO, Patanjali Food Processing Unit and Institutional Plot Sectors are located. Sectors have been planned for residential and institutional plots on both sides of this road. It is the main road to reach Jewar airport via various sectors.

(b) 100 m wide road

The construction work of 3.50 km length from Yamuna Expressway is complete. There are residential plots of Sector-18 on the left side of this road and Sector-20 on the right. The work of DBM/BC on the said road has been completed and drainage works are under progress.

Road number 17